Upcoming Road Work on Admiral Way

Please note that work for the restriping of Admiral is starting on September 26th… this may impact parking for pickup/dropoff.
Map
admiralprojectmap-e1473466972940.jpg
From SDOT:
Work to re-stripe SW Admiral Way between California and 63rd Ave SW will occur the week of September 26. We expect construction to take about one week, depending on the weather. During this time on-street parking will be restricted on both sides of the street between 7 AM and 5 PM for the entire length of the project. This allows the street to be restriped while keeping a travel lane in each direction open. “No parking” signs will be in place for 72 hours prior to the start of the restrictions. We’ll work to reduce impacts as much as possible and appreciate your patience during this work.

See more on the installation here.

 

Leave a Reply

Your email address will not be published. Required fields are marked *